Scheduled Maintenance


Recommended Posts

Just received this email from the data center the BestTechie server is located:

- Maintenance window:

Start Date and Time: 2008-Aug-17 02:00 EST

End Date and Time: 2008-Aug-17 04:00 EST

Action and Reason: Edge router hardware upgrade for increased capacity

Location of work: New York, US.

Description of work: Webair will be upgrading a customer facing edge

router, installing additional 10 Gigabit interfaces. Service will be failed

over to a redundant router during the maintenance window.

Client Impact:

Clients may experience brief packet loss while service is switched to the redundant

routers and back. We have taken every precaution to ensure that your service will not be effected.

Please note that the maintenance window is scheduled for off peak hours as well.

Just thought I would inform everyone. :)